What are you waiting for?
What was their response?
It to be completed, installation date was 14th August
They didn't have the datalogger when it was first installed, then a couple of weeks later they did, but couldn't access it as they didn't have a Installer code, in the end I contacted Growatt who provided me one, which I am still using.
It then didn't work with the Growatt battery as they had thrown away the small terminators that needed putting into the battery network ports so that the battery knew it was the only one there. I ended contacting a Growatt installer in London who generously sent me 2 free in the post, which as soon as I fitted them got the system sort of working.
The battery then charged overnight from the grid, so again I contacted Growatt support, who changed the configuration form battery first to load first (I think)
The single CT clamp was put in the wrong connecting cables
The second CT clamp is still outstanding, the system will not correctly fully function until it has been fitted, been promised this since end of August
I have no MCSE certifications
I have no DNO certifications
As I don't have the above 2, I am giving my excess to Octopus for free
I have no bird netting (trivial & in this area not sure it's necessary)
I was sold the system on the specific requirement that it would be seamless in the event of a power cut, we had a power cut, the system shut down!
I am emailing them on each Monday & Friday morning, I'm no longer getting a response.
But apart from that I'm very happy with the installation.